    Lavazinc EP two component zinc rich epoxy primer for steel reinforcement by MATEX

    Lavazinc Ep

    Zinc Rich Epoxy Primer

    LAVAZINC EP is a high-performance, zinc-rich epoxy primer designed to protect exposed reinforcement steel prior to concrete repair. This two-component system offers excellent adhesion and forms a waterproof, chemical-resistant barrier upon curing. Using sacrificial anode technology, LAVAZINC EP delivers long-lasting corrosion protection in a single coat. It is ideal for use in humid or marine environments due to its fast-curing and high-zinc formulation. Its superior mechanical properties enhance durability, making it a critical preparatory step in reinforced concrete restoration, particularly in aggressive and chloride-rich conditions.

    Technical data:
    • Color : Grey
    • Recommended film thickness : 50 – 100 microns DFT
    • Recoating interval : 2-3 hours
    • Drying time : 4-6 hours
    • Coverage : 10 m² per liter at 60 micron DFT
    • Packaging : 1 liter kit

    How to Apply Lavazinc Ep

    Lavazinc EP is a two-component zinc rich epoxy primer brushed onto fully cleaned reinforcing steel.

    1. Clean the steel. Reinforcing bars must be clean of dirt, residue, weak concrete, grease and rust. Clean with a steel brush, or sand blast if that is not sufficient, removing all rust.
    2. Mix. Mix the two pre-weighed components thoroughly until a homogeneous mixture is reached.
    3. Apply. Coat the steel immediately after cleaning, using a brush and ensuring full coverage of the rebar or steel surface. Do not apply a thick coat in a single application.
    4. Second coat. One rich coat is normally sufficient, but two coats are advisable to guarantee protection. Apply the second coat once the first is totally dry.
    5. Follow-on work. Apply repair mortars once the coat is totally dry. When used as a primer, ensure it is fully cured before applying the finishing top coat.
    6. Clean tools. Clean tools and equipment with Armosolvent before the material hardens. Hardened material can only be removed mechanically.

    Summary of the method in the Lavazinc Ep Technical Data Sheet. Always follow the full TDS on site.

    Frequently Asked Questions

    What is the coverage of Lavazinc EP?

    Theoretical coverage is 10 m² per liter at 60 micron dry film thickness. The recommended film thickness is 50-100 microns DFT.

    What is the recoating interval and drying time of Lavazinc EP?

    The recoating interval is 2-3 hours and drying time is 4-6 hours. High temperature reduces pot life and drying time.

    How many coats of Lavazinc EP are needed?

    One rich coat is normally sufficient, but the TDS advises two coats to guarantee protection, with the second applied once the first is totally dry.

    What is the minimum application temperature for Lavazinc EP?

    The minimum temperature for application is 5°C.

    Can Lavazinc EP be applied over rusty steel or existing coatings?

    No. It should not be applied on a rusty surface or existing coating, otherwise the applied coatings will peel off.